About the Project
The WARB team will be handing over this project on the 17th of November 2022.
The substation had a complete overhaul as most of the switchgear have been in operation for over 80 years.
Two new 6600kVA transformers have been installed. The entire Distribution Board have been replaced as well as a new Ring Main Unit.
Installation have been done according to schedule and we are proud to say our team did a superb job.
Thank you very much to each member of the team that was involved in delivering this truly amazing project.
Included in project:
- Replacement of 2 x 6600kVA Transformers
- New Ring main unit
- Complete new Distribution Board